Torino Commercial Solar

Tags :Cold Storage

Client: Torino


Torino and Solar Bay partner to drive down electricity expenditure with a Commercial Solar Solution.

Torino Commercial Solar Overview

Electricity a major expense for cold storage operators.

99.9kW maximum size under STC (upfront subsidy).

Estimated production of 137,000kWh per year.

System lifetime savings apx, $548,000

Creating a competitive advantage for Torino in the cold storage industry.

The Challenge

With the price of electricity increasing and being the highest input into cold storage, Torino was investigating how commercial solar could help.

The Equipment

Fronius Inverters

allmax

Trina 275 watt panels

grid-preotection-box

Grid Protection Unit

Production - Daily

The Process

01
Site Visit

During the initial site visit Solar Bay collects information on the existing electricity contracts, roof weight bearing and generation capacity, buildings electricity consumption profile, and most importantly the client goals.

02
Analysis

Torino's biggest goal was to reduce total electricity expense through investing in energy projects with strong ROI's. Solar Bay's analysis showed a 99.9kW system would have the highest ROI, with zero export to the grid.

03
Grid Connection Application

As the building was recently constructed full electrical as builts were available, and the grid application for embedded generation was straight forward.

04
Structural Engineering Certificate

Solar Bay worked with the original structural engineers to design the panel placement, 99.9kW was located on one wing of the building to allow future solar to be added if deemed commercially feasible.

05
System Design

Three Fronius 27.0kW inverters were each wired with 33.3kW of solar modules, the Switchboard location allowed for a straightforward wiring run and install.

06
Safety

Safety was taken into consideration from the first site visit. All measures were put in place for OHS, working at heights and electrical safety.

07
Installation

After identifying the location for the inverters and cabling, the team worked for two weeks to install the system.

08
Handover

A detailed handover and instruction manual was provided to Torino to ensure all of their questions could be answered.

Related Projects

Radcoflex Australia

Radcoflex Australia

A 60kW system reduced energy costs and allowed for a network tariff change.

View Project

Bing Lee Hydropanels

Bing Lee Hydropanels

A significant investment was made back into the company for future competitiveness.

View Project

BBC Plastics

BBC Plastics

100% self consumption 100kWp solar system.

View Project
×
  • Download our free guide to
    power purchase agreements 7 things you must know when dealing with PPA

×
  • Download our free guide to
    power purchase agreements 7 things you must know when dealing with PPA